Project Title: Project Diary of Cottage Extension Date Added: 15/10/2008
Daily up date of building progress. Day 1 15/10/2008, Site ready for starting extension
Step 1: First day Trade/Capability:
Take down old utility room, remove roof and take down walls
Step 2: Demolition of old utility room Trade/Capability:
Knock down old utility room, remove roof and walls put tiles and bricks to one side for re-use later
Step 3: Utiliy room down and stairs boxed in Trade/Capability:
Demolition of utility room nearing completion, we had to box the end of the stairs in and weather proof.
Step 4: Set out foundations Trade/Capability:
Setting out the profiles ready for the excuvation of the trenches
Step 5: Foundation trenches Trade/Capability:
Foundation Trenches dug and ready for concrete.
Step 6: Concreting Foundation Trade/Capability:
Concreting foundation with concrete pump.